| between Boone Rd SE and Hilfiker Lane | 5/16/2013 | 5/20/2013 | 8:30 AM | 3:30 PM | Thursday, May 16, 2013, through Wednesday, May 22, 2013, 8:30 AM to 3:30 PM daily, there will be various lane closures at the following locations for tree trimming around power lines. Commercial Street SE between Boone Rd SE and Hilfiker Lane SE: Thursday, May 16, 2013, through Monday, May 20, 2013, North bound traffic will be reduced to one lane. Liberty Street SE between Hrubetz Road SE and Browning Avenue SE: Monday, May 20, 2013, through Wednesday, May 20, 2013, North bound traffic will be reduced to one lane.
|
| Between State Street and Bellevue Street SE | 5/22/2013 | 5/22/2013 | 8:30 AM | 3:30 PM | 12th Street SE between State Street and Bellevue Street SE will have the southbound lanes of traffic reduced to one lane. Expect congestion and use another route if possible. This lane closure is for installation of utilities. |
| Between Rex St S and Mt View Dr S | 5/8/2013 | 5/22/2013 | 24/7 | 24/7 | Sidewalk closure for sewer service repair. |
| Between Hrubetz Road SE and Browning Avenue SE: | 5/20/2013 | 5/22/2013 | 8:30 AM | 3:30 PM | Thursday, May 16, 2013, through Wednesday, May 22, 2013, 8:30 AM to 3:30 PM daily, there will be various lane closures at the following locations for tree trimming around power lines. Commercial Street SE between Boone Rd SE and Hilfiker Lane SE: Thursday, May 16, 2013, through Monday, May 20, 2013, North bound traffic will be reduced to one lane. Liberty Road SE between Hrubetz Road SE and Browning Avenue SE: Monday, May 20, 2013, through Wednesday, May 20, 2013, North bound traffic will be reduced to one lane.
|
| Between Norway St NE and Shipping St NE | 5/22/2013 | 5/22/2013 | 8:30 AM | 3:30 PM | Summer Street NE between Norway Street NE and Shipping Street NE will be reduced to one lanes of traffic. Expect congestion at this location. This lane closure is for tree trimming around power lines. |
| Between Marion St NE and Center St NE | 4/22/2013 | 5/24/2013 | 24/7 | 24/7 | Sidewalk closure for installation of drain lines. |
| At the intersection of Portland Road NE | 5/20/2013 | 5/24/2013 | 8:30 AM | 3:30 PM | Hyacinth Street NE at the intersection of Portland Road NE will have the east bound right turn lane closed. Right turns will still be allowed at this location. Expect congestion at this location. Local access will be maintained at all times. This lane closure is for utility and traffic signal work as part of the Hawthorne Avenue NE/ Hyacinth Street NE Corridor Improvements Project. |
| Between 8th St NW and 6th St NW | 5/20/2013 | 5/27/2013 | 8:30 AM | 3:30 PM | Lanes of traffic narrowed for sewer service repair. |
| Between High St NE and Liberty St NE | 5/22/2013 | 5/28/2013 | 8:30 AM | 3:30 PM | Court Street NE between High Street NE and Liberty Street NE will be reduced to two lanes of traffic. Expect congestion at this location. This lane closure is for a sewer service repair. |
| Between Battle Creek Road SE and 27th Avenue SE | 5/24/2013 | 5/30/2013 | 8:30 AM | 3:30 PM | Boone Road SE between Battle Creek Road SE and 27th Avenue SE will be reduced to one lane of traffic with flaggers. Expect congestion at this location. This lane closure is for installation of utilities as part of a development project. |
| Between Airport Road and 37th Avenue | 5/24/2013 | 5/31/2013 | 8:30 AM | 3:30 PM | State Street will have east bound traffic reduced to one lane at various locations between Airport Road and 37th Avenue. Expect congestion at this location. These lane closures are for utility locate work. |
| At Simpson St SE | 5/1/2013 | 6/1/2013 | 7:00 AM | 7:00 PM | Lanes of traffic narrowed for installation of sidewalks. |
| Between Owens St S and Minto Brown Park Entrance | 5/6/2013 | 6/6/2013 | 7:00 AM | 7:00 PM | Sidewalk construction activities will begin along the east side of River Road S, near the terminus of Miller Street S, during the week of May 6, 2013. Motorists should use caution as this work will require lane closures on River Road S at Miller Street S. Travel lanes will be intermittently closed, narrowed, and shifted to facilitate work within the construction area. Bike lanes will be periodically closed and cyclists will be signed to merge with other traffic. At times, flaggers will be present to control traffic. This work will create traffic congestion within the area and motorists should expect delays. Pedestrian traffic should expect sidewalk closures within the work zone and signed detour routes. Normal work hours are 7 a.m. through 7 p.m., Monday through Friday. Additionally, the speed limit will be reduced to 25 miles per hour on River Road S, from approximately 800 feet south of Miller Street S, to just north of Miller Street S (see attached map). The speed limit reduction will begin on May 6, 2013, and will remain in affect until the work is completed in June 2013. The Keep Salem Moving! Streets and Bridges Bond, passed by Salem voters in November 2008, provided funds for improvements to sidewalks and bicycle lanes to improve safety to schools and parks. Please contact Will Kuenzi, P.E., Engineering Associate at 503-588-6211 or wkuenzi@cityofsalem.net for additional information. |
| Between State St and Court St NE | 5/3/2013 | 6/30/2013 | 24/7 | 24/7 | Sidewalk and parking lane closure for building remodel. |
| Between Lancaster Dr NE and 45th Av NE | 2/25/2013 | 9/15/2013 | 8:30 AM | 3:30 PM | Monday, February 25, 2013, through Monday, April 15, 2013, 8:30 AM to 3:30 PM daily, the following corridor will have various lane closures for utility work as part of the upcoming Market St. NE/Swegle Rd. NE Realignment & Corridor Improvements Project. Market Street NE, between Clay Street NE and 45th Avenue NE 45th Street NE, between Market Street NE and Swegle Road NE Swegle Road NE, between 45th Avenue NE and Royalty Drive NE The impacts to traffic will primarily be reduced to one lane of traffic with flaggers and lanes of traffic narrowed and shifted. Expect congestion and use another route if possible.
|
| Between Market St NE and Swegle Rd NE | 2/25/2013 | 9/15/2013 | 8:30 AM | 3:30 PM | Monday, February 25, 2013, through Monday, April 15, 2013, 8:30 AM to 3:30 PM daily, the following corridor will have various lane closures for utility work as part of the upcoming Market St. NE/Swegle Rd. NE Realignment & Corridor Improvements Project. Market Street NE, between Clay Street NE and 45th Avenue NE 45th Street NE, between Market Street NE and Swegle Road NE Swegle Road NE, between 45th Avenue NE and Royalty Drive NE The impacts to traffic will primarily be reduced to one lane of traffic with flaggers and lanes of traffic narrowed and shifted. Expect congestion and use another route if possible.
|
| Between 45th Av NE and Royalty Dr NE | 2/25/2013 | 9/15/2013 | 8:30 AM | 3:30 PM | Monday, February 25, 2013, through Monday, April 15, 2013, 8:30 AM to 3:30 PM daily, the following corridor will have various lane closures for utility work as part of the upcoming Market St. NE/Swegle Rd. NE Realignment & Corridor Improvements Project. Market Street NE, between Clay Street NE and 45th Avenue NE 45th Street NE, between Market Street NE and Swegle Road NE Swegle Road NE, between 45th Avenue NE and Royalty Drive NE The impacts to traffic will primarily be reduced to one lane of traffic with flaggers and lanes of traffic narrowed and shifted. Expect congestion and use another route if possible.
|